| Items to Complete |
|
Completed Items |
| Install Waynes coating on walls |
|
Installed floor in radio room and main room
11/05 |
| Install flooring in kitchen |
|
Installed recessed lights in main room 11/05 |
| Install top coat of flooring |
|
Installed ceiling fan in main room 11/05 |
| Paint porch |
|
Installed 2 outside lights 11/05 |
| Fix kitchen roof |
|
Painted door 04 |
|
|
Chimney caps made & installed - Thanks
Kevin! 11/05 |
|
|
All wiring finished, including outlets and
lights 11/05 |
|
|
Alarm wiring finished 11/05 |
|
|
Planed all cabinet and interior doors so
they shut tight |
|
|
Installed new doorknob on radio room door |
|
|
Paint walls and ceilings |
|
|
Install alarm panel and cameras |
|
|
Install sump-pump |
|
|
|
|
|
|